HIS Project Update June 13, 2008

Water Street East - Prescott Street to Cochrane Street

Water Street east of Prescott Street to Cochrane Street should be open to through traffic by no later than July 1. The City of St. John's plans to have the topcoat of pavement laid on Water Street east from Prescott Street to Gills Cove prior to the Cochrane Street intersection at Water Street being opened to through traffic.

Starting Monday Modern Paving will have its carpenters on site raising manholes on the section of Water Street from Prescott Street to Gills Cove at the same time getting the intersection of Cochrane Street and Water Street ready for base coat paving.

Access to all businesses and parking in the area will be maintained at all times.

HIS work continues on Water Street east moving in both directions. A crew is in place at the far east of Water Street near Temperance Street moving west while a crew continues to move east on Water Street from Cochrane Street to Hill O’Chips.

Work continues on Harbour Drive and Waldegrave Street moving east on Harbour Drive.

For more information on the HIS Project call Access St. John's at 311 of visit www.stjohns.ca